  1. Click the Ellipsis icon at the top-right corner of the Datasets table and select Export Project Output.

    Image Added
  2. The Export Project modal appears.

    Image RemovedImage Added

2 3. All is selected by default for Select Batch.

3 4. Select CSV from the list for Select format.

4 5. Select the field(s) you want to export for Select fields. By default, all the fields will be exported.

5 6. (Optional) Select the values for Start date and End date.

6 7. Selectthe Completed tasks only checkbox to download the data associated with only the completed tasks in your project. If not selected, all the tasks will be exported.

7 8. Click Download to trigger the export. Once the export completes, the modal notifies you and offers a link to download the exported content.

...

8 9. Click Download File to download the exported output.

9 10. Click Close to return to the Dataset tab.

...